EPA Approves Cleanup Plan for Remaining Coal Ash at TVA
Contact Information: Davina Marraccini, (404) 562-8293, marraccini.davina@epa.gov
(
The cleanup plan approved by EPA in a signed Action Memorandum (AM) was chosen above the others because of its protectiveness, ease of implementation and cost effectiveness.
The cleanup plan includes:
Removal and On-Site Storage: The cleanup plan calls for the removal and consolidation of approximately 2.5 million cubic yards of ash from the embayment. All the ash will be consolidated on-site in the re-engineered TVA coal ash disposal area, and no material will be taken off-site—eliminating potential impacts associated with off-site disposal. The cleanup plan virtually eliminates the risks and costs associated with shipping ash over public roads or by rail. Keeping all the ash on site will minimize heavy truck traffic in the
Building Protective Perimeter Dike: TVA will place dry ash atop an engineered base layer of sand, gravel and geo-fabric. The dry ash will be placed into the on-site disposal area slowly so that it does not slide. A new dike will be installed around the entire perimeter of the coal ash disposal area to keep the ash from entering the embayment in the future. This dike will go 60 to 70 feet below the ground to the shale bedrock, and will consist of overlapping soil-cement columns that are able to withstand a local 6.0 magnitude earthquake. The coal ash area will incorporate measures to divert drainage and control runoff.
Closing the Disposal Area: Once all the ash has been put in place, a two-foot clay cover and one foot of top soil will be put over it. Vegetation will then be planted to prevent erosion. Upon completion, the structure will be closely monitored, and regularly inspected to ensure public health and safety. Long-term groundwater monitoring will be conducted.
The height of the closed coal ash disposal area will be approximately 25 feet above the road surface, which is about 30 feet lower than the former dredge cell. The ash pond will be closed at the same time as the former dredge cell. Closing the areas simultaneously will eliminate the need for imported fill material to close the ash pond, which is expected to result in schedule efficiencies and cost savings.
Restoration: Following the removal of ash to native sediments, the embayment ecosystem will be restored to conditions that protect human health and the environment. This includes the restoration of a complex mosaic of forested, scrub-shrub and emergent wetland plant communities that will provide diverse habitats for fish, semi-aquatic amphibians and bird species.
Drinking water, river water and groundwater in the area are sampled on a routine basis, and current results indicate no exceedances of drinking water standards or surface water quality criteria. Continued ecological, groundwater and river sampling will be conducted indefinitely after the cleanup is complete to monitor environmental conditions surrounding the site.
Field work to prepare for the cleanup is expected to begin in late May as the time-critical work on the site concludes. This portion of the cleanup is estimated to take about four years to complete and will cost approximately $268.2 million, which includes an estimated $686,000 in annual maintenance costs for the first 30 years once the cleanup is complete. Ongoing five-year reviews will be conducted to ensure the integrity of the ash containment.
The Action Memorandum and associated materials are posted on the EPA’s Web page at: www.epakingstontva.com. They are also available for review at the
Public comments were sought on the Engineering Evaluation/Cost Analysis (EE/CA) Report and the alternatives described in it to restore the environment. TVA’s responses to all comments received can be found in the responsiveness summary, an appendix to the Action Memorandum. Public comments on the AM itself are being accepted through June 18, 2010, and should be submitted via email to kingstoncomm@tva.com or in writing to:
TVA
The AM will be the subject of a public meeting on Thursday, May 20, at the
A separate EE/CA Report for the residual ash in the river system that remains once the time-critical dredging is complete will be prepared at a later date.
Note: If a link above doesn't work, please copy and paste the URL into a browser.
View all Region 4 News Releases
BP Oil Spill Response: Web site | Get email updates
| You can view or update your subscriptions or e-mail address at any time on your Subscriber Preferences Page. All you will need is your e-mail address. If you have any questions or problems e-mail support@govdelivery.com for assistance. This service is provided to you at no charge by U.S. Environmental Protection Agency. |
| ||||||
This email was sent to ##email##.
Sent by the U.S. Environmental Protection Agency · 1200 Pennsylvania Avenue NW · Washington DC 20460 · 202-564-4355
No comments:
Post a Comment